Commercial kitchen ventilation startup checklist.

A practical readiness and closeout list for hoods, exhaust fans, makeup air, controls, VFDs, and airflow testing.

Checklist

Open only the project stage you need.

Use this list before startup and again before the final closeout visit.

Mechanical readinessHoods, fans, duct connections, access, belts, filters, and dampers.+

Hoods, exhaust fans, and makeup-air equipment are installed

Fan wheels turn freely and belts, sheaves, bearings, and guards are in place

Filters, grease extractors, access panels, and dampers are installed

Roof and mechanical-room access is available and safe

Duct connections and fan discharge are visibly complete

Electrical & controlsPower, starters, VFDs, sensors, interlocks, and control drawings.+

Permanent power is available at fans, controls, VFDs, and connected equipment

Disconnects, starters, overloads, and VFDs are installed and labeled

Hood controls, sensors, switches, and low-voltage wiring are complete

Exhaust and makeup-air interlocks are ready to test

Current wiring diagrams and sequence-of-operation documents are on site

Operational testingRotation, amperage, commands, airflow, capture, and pressure.+

Confirm fan rotation before extended operation

Record motor amperage and VFD operating frequency

Verify exhaust and makeup air start, stop, and modulate as intended

Check hood capture while the relevant cooking equipment operates

Observe door pressure, cross-drafts, supply-air interference, noise, and vibration

Closeout packageSettings, readings, faults, corrections, and open responsibilities.+

Record equipment manufacturer, model, serial number, and serving area

Save VFD settings, control configuration, fault history, and final operating state

Document airflow readings and test conditions when included in the scope

Separate completed corrections from open trade or installation deficiencies

Assign each open item and confirm the required retest or follow-up

Avoid the Failed Visit

Five conditions that stop productive startup.

No permanent power at fans or controls

Missing VFD, starter, sensor, or interlock wiring

Unsafe or unavailable roof access

Other trades still changing the operating sequence

No current drawings, equipment schedule, or responsible project contact

Need TCS to run the startup or performance test?

Send the site address, equipment schedule, controls information, project status, and required completion date.

This checklist supports project readiness. It is not an official FDNY inspection, fire-suppression certification, engineering design, or guarantee of approval.